1000 Complex Roof/HVAC Replacement – 9-29-18 Weekly Construction Update
September 29, 2018 · Construction Updates, SLO 1000 Complex Renovations
Installation of the controls for the mechanical equipment is ongoing, and the team began installing T-stats in buildings 1000 and 1300. Startup is scheduled for 10/9/18. The temporary fencing has been removed from around buildings 1000 and 1300.
Download PDF →