Project Start Date: April 11, 2016 Project Completion Date: Fall 2017This new 32,000 square foot, two-story structure was built in order to house the programs and offices displaced by the removal of modular structures. The first floor of this structure is comprised of eight high-capacity multi-discipline classrooms capable of serving up to 50 students each. It also has one forum-size classroom with a full capacity of 80 students. The second floor of the structure consists of more than 40 offices, a large staff lounge area and three meeting rooms. Construction commenced on April 11, 2016 with completion in the fall of 2017 and opening in the spring of 2018.
Project Updates - View all Project Updates →
January 2018 Monthly Project Update
February 1, 2018SLO Instructional Building – 01-12-18 Weekly Construction Update
January 12, 2018SLO Instructional Building – 01-05-18 Weekly Construction Update
January 5, 2018Recent Project Images
View All1 of 111 X
2 of 111 X
3 of 111 X
4 of 111 X
5 of 111 X
6 of 111 X
7 of 111 X
8 of 111 X
9 of 111 X
10 of 111 X
11 of 111 X
12 of 111 X
13 of 111 X
14 of 111 X
15 of 111 X
16 of 111 X
17 of 111 X
18 of 111 X
19 of 111 X
20 of 111 X
21 of 111 X
22 of 111 X
23 of 111 X
24 of 111 X
25 of 111 X
26 of 111 X
27 of 111 X
28 of 111 X
29 of 111 X
30 of 111 X
31 of 111 X
32 of 111 X
33 of 111 X
34 of 111 X
35 of 111 X
36 of 111 X
37 of 111 X
38 of 111 X
39 of 111 X
40 of 111 X
41 of 111 X
42 of 111 X
43 of 111 X
44 of 111 X
45 of 111 X
46 of 111 X
47 of 111 X
48 of 111 X
49 of 111 X
50 of 111 X
51 of 111 X
52 of 111 X
53 of 111 X
54 of 111 X
55 of 111 X
56 of 111 X
57 of 111 X
58 of 111 X
59 of 111 X
60 of 111 X
61 of 111 X
62 of 111 X
63 of 111 X
64 of 111 X
65 of 111 X
66 of 111 X
67 of 111 X
68 of 111 X
69 of 111 X
70 of 111 X
71 of 111 X
72 of 111 X
73 of 111 X
74 of 111 X
75 of 111 X
76 of 111 X
77 of 111 X
78 of 111 X
79 of 111 X
80 of 111 X
81 of 111 X
82 of 111 X
83 of 111 X
84 of 111 X
85 of 111 X
86 of 111 X
87 of 111 X
88 of 111 X
89 of 111 X
90 of 111 X
91 of 111 X
92 of 111 X
93 of 111 X
94 of 111 X
95 of 111 X
96 of 111 X
97 of 111 X
98 of 111 X
99 of 111 X
100 of 111 X
101 of 111 X
102 of 111 X
103 of 111 X
104 of 111 X
105 of 111 X
106 of 111 X
107 of 111 X
108 of 111 X
Project Documentation
Notice to Proceed
A notice to proceed for the Cuesta College San Luis Obispo Instructional Building project was sent to the following firms on April 8, 2016:
Bid Package 1, 4, & 5 – Wysong Construction Company
Bid Package 2 – Kern Steel Fabrication, Inc.
Bid Package 3, 6, & 12 – Newton Construction & Management, Inc.
Bid Package 7 – R. F. Koerber, Inc.
Bid Package 8 – Floor Connection, Inc.
Bid Package 9 – Tarlton & Son, Inc.
Bid Package 10 & 11 – Brannon, Inc. dba Smith Electric Service
Bid Package 13 – G.F. Garcia & Sons, Inc.
Bid Package 14 – Toyon Landscapes, Inc.
Notice of Award
A notice of award related to Cuesta College San Luis Obispo Instructional Building project was sent to the following firms on March 31, 2016:
Bid Package 1 – Structural & Site Concrete
- Wysong Construction Company
Bid Package 2 – Structural Steel, Metal Deck, & Misc. Metal
- Kern Steel Fabrication, Inc.
Bid Package 3 – General Trades
- Newton Construction & Management, Inc.
Bid Package 4 – Roofing
- Wysong Construction Company
Bid Package 5 – Glass & Glazing
- Wysong Construction Company
Bid Package 6 – Lath, Plaster, & Gypsum Board Assemblies
- Newton Construction & Management, Inc.
Bid Package 7 – Acoustic & Metal Ceilings
- R. F. Koerber, Inc.
Bid Package 8 – Flooring
- Floor Connection, Inc.
Bid Package 9 – Painting
- Tarlton & Son, Inc.
Bid Package 10 – Fire Sprinklers
- Brannon, Inc. dba Smith Electric Service
Bid Package 11 – Plumbing & Mechanical
- Brannon, Inc. dba Smith Electric Service
Bid Package 12 – Electrical
- Newton Construction & Management, Inc.
Bid Package 13 – Grading, Paving Demolition & Utilities
- G.F. Garcia & Sons, Inc.
Bid Package 14 – Landscape
- Toyon Landscapes, Inc.
Notice of Intent
A notice of intent to award the Cuesta College San Luis Obispo Instructional Building project to was sent to the following non-awardees on March 28, 2016:
Bid Package 1 – Structural & Site Concrete
- Newton Construction & Management, Inc.
Bid Package 2 – Structural Steel, Metal Deck, & Misc. Metal
- Golden State Steel, Inc.
Bid Package 3 – General Trades
- Wysong Construction Company
Bid Package 4 – Roofing
- Newton Construction & Management, Inc.
- Pacific Builders & Roofing
Bid Package 5 – Glass & Glazing
- Pacific Glazing Contractors
- J.W. Design & Construction, Inc.
Bid Package 6 – Lath, Plaster, & Gypsum Board Assemblies
- Precon Industries
- Tarlton & Son, Inc.
Bid Package 7 – Acoustic & Metal Ceilings
- Santa Maria Acoustical
- Western Building Materials
Bid Package 8 – Flooring
- Cinderella Showcase, Inc.
Bid Package 9 – Painting
- Newton Construction & Management, Inc.
- Pro Coatings
Bid Package 10 – Fire Sprinklers
- Fire System Solutions, Inc.
- Cosco Fire Protection
Bid Package 11 – Plumbing & Mechanical
- HPS Mechanical, Inc.
- Newton Construction & Management, Inc.
Bid Package 12 – Electrical
- Brannon, Inc. dba Smith Electric Service
- Electricraft, Inc.
- Rossi & Carr Electric, Inc.
Bid Package 13 – Grading, Paving Demolition & Utilities
- Michael Frederick Paving Corporation
- R. Burke Corporation, Inc.
- Sansone Company, Inc.
Bid Package 14 – Landscape
- J.D. Humann Landscape, Inc.
- Newton Construction & Management, Inc.