District-Wide Upgrades

Project Overview

Project Start Date: Spring 2018 Project Completion Date: Spring 2021

Various district-wide upgrades will occur and include infrastructure site utilities, fiber-loop upgrades, a new gym floor, and various technology needs. The upgrades are scheduled to occur on both the North County and San Luis Obispo campuses throughout the second issuance.

                  

Project Documentation

Notice of Award – Electrical Site Infrastructure Improvements

A notice of award related to the Cuesta College San Luis Obispo Electrical Site Infrastructure Improvements project was sent to the following company on July 7, 2020:

  • Electricraft, Inc.

Notice of Intent

A notice of intent to award related to the Cuesta College, San Luis Obispo Electrical Site Infrastructure Improvements project was sent to the following non-awardees on June 15, 2020:

  • High Voltage Electric
  • Santa Maria Electric
  • Smith Electric