Repairs – HVAC/Roofs

Project Overview

Project Start Date: Spring 2015 Project Completion Date: Fall 2015

Four roofs and HVAC units were replaced on the San Luis Obispo Campus. The repairs were completed on buildings 1100, 4500, and 4600 between the summer and fall semesters of 2015.

                  

Recent Project Images

View All

Project Documentation

Notice to Proceed

A notice to proceed for the Cuesta College Roofing/HVAC Replacement project was sent to the following firms on the dates indicated below:

06/03/15 – James A Quaglino; DBA Quaglino Roofing – BP-0, Roofing Item1.1.2 (Bldg 4500) & 1.1.3 (Bldg 4600)

06/12/15 – Knecht’s Plumbing & Heating, Inc. BP-02 – HVAC

06/24/15 – Electricraft, Inc. – BP-03 Electrical

07/8/15 – Wicks Roofing, Inc. – BP-01-Roofing Item 1.1.1 (Bldg 1100)

Notice of Award

A notice of award Cuesta College Roofing/HVAC Replacement project was sent to the following firms on May 21, 2015:

  • Knecht’s Plumbing & Heating, Inc. BP-02 – HVAC
  • James A Quaglino; DBA Quaglino Roofing – BP-01, Roofing Item1.1.2 (Bldg 4500) & 1.1.3 (Bldg 4600)
  • Wicks Roofing, Inc. – BP-01-Roofing Item 1.1.1 (Bldg 1100)
  • Electricraft, Inc. – BP-03 Electrical

Notice of Intent

A notice of intent to award the Cuesta College Roofing/HVAC Replacement project to Knecht’s Plumbing & Heating, Inc. BP-02 – HVAC, James A Quaglino; DBA Quaglino Roofing – BP-01, Roofing Item1.1.2 (Bldg 4500) & 1.1.3 (Bldg 4600), Wicks Roofing, Inc. – BP-01-Roofing Item 1.1.1 (Bldg 1100), and Electricraft, Inc. – BP-03 Electrical was sent to the following non-awardees on May 15, 2015:

  • American Incorporated
  • Best Contracting Corporation
  • JR Barto Heating, AC, Sheet Metal, Inc.
  • Rossi & Carr Electrical, Inc.
  • Smith Electric Service