SLO Roofing & HVAC Upgrades
Project Overview
Project Start Date: Fall 2021 Project Completion Date: Fall 2023The SLO Campus Roofing & HVAC Upgrades project is scheduled to start Fall of 2021 through the Fall of 2023. Roofing and HVAC replacements will be completed on 6100 (Language Arts), 6300 (Humanities Forum), 7100 (Art/Music), 5100 (Cafeteria), 5200 (Bookstore), 5300 (Student Life & Leadership) and 5400 (Associated Students Auditorium). The work is anticipated to be complete in phases to minimize the disruption to District Staff, Faculty and Community.
Project Updates - View all Project Updates →
Chiller Replacement – 03-31-23
March 31, 2023Chiller Replacement – 12-2-22
December 2, 2022SLO 6100, 6300, and 7100 Roofing and HVAC – 09-09-22 Weekly Construction Update
September 9, 2022Project Documentation
Notice to Proceed
A notice to proceed for the Cuesta College North County Campus Boiler Replacement Project was sent to the following firm on December 7, 2023:
- Smith Mechanical-Electrical-Plumbing, Inc.
Notice to Proceed
A notice to proceed for the Cuesta College San Luis Obispo County Campus Building 5300 Tile Roof Replacement Project was sent to the following firm on October 6, 2023:
- Craig Roof Company, Inc.
Notice to Proceed
A notice to proceed for the Cuesta College San Luis Obispo County Campus 5000 Complex Roof & HVAC Replacement Project was sent to the following firm on August 2, 2023.
- Smith Mechanical-Electrical-Plumbing
Notice of Award – 5000 Complex Roof & HVAC Replacement Project
A notice of award related to the Cuesta College San Luis Obispo County Campus 5000 Complex Roof & HVAC Replacement Project was sent to the following firm on July 18, 2023:
• Smith Mechanical-Electrical-Plumbing
Notice to Proceed – 6100, 6300, & 7100 Re-Roofing & HVAC Replacement Project
A notice to proceed for the Cuesta College San Luis Obispo Campus 6100, 6300, & 7100 Re-Roofing & HVAC Replacement Project was sent to the following firm on September 3, 2021:
• Edwards Construction Group, Inc.
Notice of Award – 6100, 6300, & 7100 Re-Roofing & HVAC Replacement Project
A notice of award related to the Cuesta College San Luis Obispo Campus 6100, 6300, & 7100 Re-Roofing & HVAC Replacement Project was sent to the following firm on August 26, 2021:
• Edwards Construction Group, Inc.