Construction Alerts Archive

 

Buildings 2100 and 2400 Roofing

Location: San Luis Obispo Campus

Date(s) in Effect: Monday, 10/28/19 through Friday, 11/1/19 6:00AM-6:00PM

Description: Final phase of roof coping and flashing will take place on Buildings 2100 and 2400 from Monday, October 28 through Friday, November 1 from 6am-6pm. There will be no major effects to use and access of the buildings. Please be advised some noise is to be expected.



Crane Outside Building 1400

Location: San Luis Obispo Campus

Date(s) in Effect: Friday, 10/25/19 6:00AM - 6:00PM

Description: A crane will be utilized outside of Building 1400. Some parking spaces in lot 5 will be affected. Areas highlighted in yellow on the associated map will be off limits to public access. Please be advised that loud noise levels may be heard at times.



Concrete Trucks near Buildings 2100 and 4100

Location: San Luis Obispo Campus

Date(s) in Effect: Thursday, 10/24/19 7:00AM-3:00PM

Description: Concrete trucks will be on campus near buildings 2100 and 4100. Please be advised that moderate noise levels may be heard at times.



Data Center Fire Alarm Testing

Location: San Luis Obispo Campus

Date(s) in Effect: Tuesday, 10/22/19 6:00AM through 9:00AM

Description: The San Luis Obispo Campus Data Center project’s General Contractor will be testing the Data Center fire alarm for proper operation. The fire alarm test is schedule to occur from 6:00 AM through 9:00 AM on Tuesday, 10/22/19. The fire alarm will be audible at this time and is just a test. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Asphalt Work Near Buildings 4100 and 3300

Location: San Luis Obispo Campus

Date(s) in Effect: Tuesday, 10/22/19 7:00AM through 3:30PM

Description: The San Luis Obispo Campus Fiber Star contractor will be prepping, then patching, back asphalt at the walkways in the areas indicated on the associated map. Please be advised that there may be some odors and moderate equipment noise during this time. The contractor will start at approximately 7:00 am on 10/22/19 and be complete by 3:30 pm 10/22/19. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Asphalt Work Near Buildings 7500 and 9100

Location: San Luis Obispo Campus

Date(s) in Effect: Tuesday 10/22/19 7:00AM through 3:30PM

Description: The San Luis Obispo Campus Fiber Star contractor will be prepping then patching back asphalt at the walkways near the 7500 and 9100 buildings. Please be advised that there may be some odors and moderate equipment noise noticeable during this time. The contractor will start at approximately 7:00 am on 10/22/19 and be complete by 3:30 pm 10/22/19. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Building 2600 External Wireless Access Point Installation

Location: San Luis Obispo Campus

Date(s) in Effect: Friday, 10/18/19 7:00AM - 4:00PM

Description: The San Luis Obispo Campus 2000 Tech Upgrades project’s General Contractor will be completing work associated with external wireless access points and will have a lift on site to reach the install area on the side of building 2600. The crew will also need access to room 2757 to run cable to the wireless access point. The area to be affected by this work will be cordoned off as off-limits to public access. The area is highlighted in yellow on the associated map. This work will be starting on Friday, October 18th at approximately 7:00am and be complete by 4:00pm. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



2000 Complex Door Hardware and Door Replacement Work

Location: San Luis Obispo Campus

Date(s) in Effect: Saturday, 10/19/19 7:00AM through Friday, 11/08/19

Description: The San Luis Obispo Campus 2000 Complex ADA Upgrades project’s General Contractor will be completing work on door hardware and door replacement at the 2000 Complex Buildings. During this time the doors will be operational during business hours with minor exceptions. Faculty, students, staff, and guests will be directed to other entrances if necessary. The area is highlighted in yellow on the accompanying map. The work will occur on Saturday, October 19th beginning at approximately 7am and continue as night work through November 8th, 2019. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Overhead Drilling in Building 2200 Crawl Space

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 10/16/19 7:00AM - 8:00AM

Description: The San Luis Obispo Campus Fiber Star project’s general contractor will core one (1) hole in the electrical room overhead in the crawl space in building 2200. Please be advised that the equipment being used will have moderate noise levels at times during the work activity. The work will start on Wednesday, October 16th at approximately 7:00am and be complete by 8:00am. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Building 2400 Temporary Stair Closure for Painting

Location: San Luis Obispo Campus

Date(s) in Effect: Tuesday, 10/15/19 7:00AM and Saturday, 10/19/19 7:00AM

Description: The San Luis Obispo Campus 2000 Complex ADA Upgrades project’s General Contractor will be completing painting work at the stairs of the 2400 building. During this time the stairs will be closed to public access while they are painted. Faculty, students, staff, and guests will be directed to other entrances. The area is highlighted in yellow on the accompanying map. The work will occur on Tuesday, October 15th beginning at approximately 7am and again on Saturday, October 19th beginning at approximately 7am. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.