Asphalt Sidewalk Removal Around Modular Complex

Location: North County Campus

Date(s) in Effect: Wednesday, 06/12/19 through Tuesday, 06/18/19

Description: On Wednesday, June 12, 2019, the Interim Housing Demobilization project’s contractor will begin removing the asphalt sidewalks around the modular complex. This work is scheduled to occur from 7:00 AM, Wednesday, 6/12/19 to 5:00 PM Tuesday, 6/18/19. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Early Childhood Education Center Asphalt Laying

Location: North County Campus

Date(s) in Effect: Wednesday, 06/05/19 through Tuesday, 06/11/19

Description: On Wednesday June 5, 2019 the R&B Shultz Early Childhood Education Center’s General Contractor, AMG, will begin laying asphalt for the R&B Schultz Early Education Building parking lot. This work is scheduled to occur from 7:00 AM Wednesday, June 5 to 5:00 PM Tuesday, June 11. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



San Luis Obispo Campus Aquatics Center Paving

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 06/05/19 through Friday, 06/07/19

Description: On Wednesday, 6/5/19, the San Luis Obispo Aquatics Center project’s general contractor will begin exterior improvements on the asphalt in parking lot 6 and at the entrance of the service road near parking lot 5. This work will be occurring from 7:00 AM- 4:00 PM daily. Please notify all parties that this work may affect. If you have any questions, please contact Facilities Services 805-546-3283.



San Luis Obispo Campus 1000 Complex Roofing/HVAC Removal

Location: San Luis Obispo Campus

Date(s) in Effect: Thursday, 05/30/19

Description: The San Luis Obispo Campus 1000 Complex Roofing/HVAC project’s construction personnel will be using a crane to pick the HVAC equipment off the roof of building 1200. This work will be starting at 7:00 am 5/30/2019 and completing by 3:30 pm 5/30/2019. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Aquatics Center Heavy Equipment Lifting

Location: San Luis Obispo Campus

Date(s) in Effect: Thursday, 05/23/19

Description: Revised* - On Thursday, May 23, 2019, the San Luis Obispo Aquatics Center project’s general contractor will be lifting heavy equipment overhead via crane in the laydown area north of building 1400. The service road in between this area will be closed. This work will start at approximately 7:00 am and is expected to end at 4:00pm. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283. * Original work date was Wednesday, May 22, 2019



Temporary Power Shut Down – 1000 and 2000 Complexes

Location: San Luis Obispo Campus

Date(s) in Effect: Saturday, 5/18/19 - 1000 Complex 5:00 AM to 9:00 AM; 2000 Complex 9:00 AM to 12:00 PM

Description: The contractor for 1000/2000 12KV Medium Voltage Electrical Equipment Replacement (Switchgear) project will be shutting down the power to the 1000 and 2000 complexes on Saturday, 5/18/19. The power will be shut off to the 1000 complex from 5:00 AM to 9:00 AM and the power will be shut off to the impacted 2000 complex buildings from 9:00 AM to 12:00 PM. Please notify all parties that this work may affect. If you have any questions, please contact Facilities Services at (805) 546-3283.



Asphalt Overlay Project Preparation and Road Controls

Location: San Luis Obispo Campus

Date(s) in Effect: Friday, 05/31/19 through 06/09/19

Description: The San Luis Obispo Campus Road Overlay, Phase II project’s construction personnel will be mobilizing and placing erosion control on 05/31/19 in preparation for the asphalt overlay project. Beginning on Monday, 6/3/19 at 7:00 AM through 3:30 PM, Sunday, 6/9/19, one-way traffic controls will be in place and some delays are expected. The areas impacted are indicated on the associated map and include Chorro Valley Road and a portion of both Cuesta College and Hollister roads. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Early Childhood Education Center Driveway Demolition and Installation

Location: North County Campus

Date(s) in Effect: Thursday, 4/25/19 through Friday, 5/10/19

Description: On Thursday, April 25, 2019 the R & B Shultz Early Childhood Education Center’s general contractor will begin the demolition and installation of the driveways for the R&B Schultz Early Education Building parking lot. Two sections of the existing sidewalk, along Dallons Drive will be closed for approximately two weeks during construction of the driveways. This work is scheduled to occur from 7:00 AM, Thursday, April 25, 2019 through 5:00 PM, Friday, May 10, 2019. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Data Center Gas Line Work

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 4/17/19 through Thursday, 4/18/19

Description: The San Luis Obispo Campus Data Center project’s General Contractor will be completing work associated with the natural gas line that will feed Data Center’s new generator. The area to be affected by this work will be cordoned off to public access. The area impacted is highlighted in on the associated map. This work will be begin on 4/17/19 at 7:00 am and complete by 5:00 PM on 4/18/19. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



Planned Internet Outage – Buildings 9100 and 9200

Location: San Luis Obispo Campus

Date(s) in Effect: Friday, 4/05/2019 through Saturday, 4/06/2019

Description: The San Luis Obispo Campus Athletic Fields Wireless & TR Upgrades project’s construction personnel will be switching over to the new data IDF rack. Affected buildings (9100/9200) will have no internet during this time. This work will be starting Friday (4/5/2019) at 3:00pm and completing by Saturday (4/6/2019) at 4:00pm. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.