Construction Alerts Archive

 

New Cabling Install in Building 3300

Location: San Luis Obispo

Date(s) in Effect: 3/21/23 – 3/24/23, 7am – 4pm

Description: Contractor will be installing new cabling both overhead and below the raised floor in Building 3300. Several ceiling and floor tiles will need to be removed and reinstalled. There will be limited access for the duration of the work. Some noise is to be expected.



Power Shutdown at Chiller Yard & Data Center

Location: San Luis Obispo

Date(s) in Effect: 3/24/23, 7am-2pm

Description: Contractor will disconnect the temporary chiller and make final connections to the new chillers. Please be advised power will be shut down at the chiller yard as well as the Data Center for the duration of this work. A back-up generator will provide power to the data center during this outage. Area of work is noted on the associated map. Noise is to be expected.



Electrical Work in Building 6300 (Room 6304)

Location: San Luis Obispo

Date(s) in Effect: 3/20/23 – 3/24/23, 7am - 4pm

Description: Contractor will be performing electrical work in 6304 classroom. Please be advised lighting will be unavailable for the duration of this work. Noise is to be expected.



Fire Alarm Testing at Buildings 4100, 4200, and 4300

Location: San Luis Obispo

Date(s) in Effect: 3/3/23, 10am-4pm

Description: Contractor will perform fire alarm testing in Buildings 4100, 4200 and 4300. Please be advised audible/visuals will be set off at all three buildings. Restrooms at each of these locations will be closed for a short period while testing is being performed. Area of work is noted on the associated map.



Roof Repairs on Building 6100

Location: San Luis Obipos

Date(s) in Effect: 3/1/23 – 3/3/23, 6am-5pm

Description: Contractor will be performing roof repairs at two locations and remove debris from a third location on Building 6100. Please be advised walkways noted on the associated map will be partially closed. ADA pathways will be maintained to the fullest extent possible. remove roofing, replace necessary substrate, and reinstall roofing. Loud noise is to be expected due to hand and power tools being used.



Rework on Fire Alarms in Buildings 4100, 4200, 4300

Location: San Luis Obispo

Date(s) in Effect: 2/27/23, 7am-4pm

Description: Contractor will be on site to perform rework on fire alarms in Buildings 4100, 4200 and 4300. Please be advised no audible/visuals will be sounded at this time. Area of work is noted on the associated map.



8100 Modular Building Removal

Location: San Luis Obispo

Date(s) in Effect: 2/20/23 – 3/2/23, 7am-4pm

Description: The contractor will be onsite to separate and haul away the 8100 modular building. The area of work is identified on the map below. Although Parking Lot 4 will remain open, the contractor will be utilizing portions of the lot for staging and access purposes. Noise is to be expected.



Fire Alarm Pre-Testing in Buildings 4100, 4200,4300, and 5400

Location: San Luis Obispo

Date(s) in Effect: 2/17/23 & 2/20/23, 7am-4pm

Description: On February 17, 2023 the contractor will perform fire alarm pre-testing in Buildings 4100, 4200, and 4300. The contractor will return on February 20, 2023 to install and pre-test fire alarm devices in Building 5400. Please be advised alarm will be audible and visible strobes will be set off at these locations during this time of work. Area of work is noted on associated map.



HVAC Rooftop Work at Building 4000

Location: San Luis Obsipo

Date(s) in Effect: 12/27/22 - 12/28/22

Description: Contractor will install powered exhaust units at the rooftop of Building 4000. This work will require interior access in multiple areas of the Building. Please be advised heating & AC will be interrupted for the duration of this work. Area of work is noted on the associated map. Noise is to be expected.



Demo Work at Building 6200 Restrooms

Location: San Luis Obsipo

Date(s) in Effect: 12/27/22 – 2/17/23

Description: Contractor will begin demolition and reconstruction work in both the men’s & women’s restrooms at Building 6200. Work will take place throughout the day & evenings. Please be advised restrooms will be closed for the duration of this work. Area of work is noted on the associated map. Noise is to be expected.