Construction Alerts Archive

 

Ansul Pull-Station Alarm System Testing

Location: North County Campus

Date(s) in Effect: Wednesday, 5/9/18 from 8:00 AM through 4:00 PM

Description: The North County Campus Center project’s construction personnel will be testing the Ansul pull-station alarm system on Wednesday, 5/9/18. This will require testing of the audible alarms at the Campus Center and may be heard throughout the campus. Please notify anyone that this work may impact.



SLO Campus Women’s Locker Room Closure

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday 5/16/18 through Thursday 5/17/18

Description: Building 1100 Women’s Locker Room will be closed from Wednesday, May 16, 2018 through Thursday, May 17, 2018 for construction. Please use the temporary women’s locker room identified in building 1000.

THE LOCKERS IN THE WOMEN’S LOCKER ROOM WILL BE INACCESSIBLE FROM WEDNESDAY, 5/16/18 – THURSDAY, 5/17/18.

PLEASE REMOVE ALL PADLOCKS & PERSONAL BELONGINGS FROM BUILDING 1000 ON OR BEFORE TUESDAY, 5/15/18.

Please contact Facilities Services (805) 546-3283 if you have any questions.



North County Campus Parking Lot Paving

Location: North County Campus

Date(s) in Effect: Thursday 4/12/18 through Friday 4/20/18

Description: The Campus Center project’s construction personnel are scheduled to start asphalt paving operations connecting Parking Lot 10 and Parking Lot 11 and a small patch back area in Parking Lot 11 as shown by the yellow highlighted area. The majority of this work will occur within the construction fence with the exception of the small Parking Lot 11 work. Please expect smell from the asphalt fumes, noise and increased truck traffic during this activity. This work is expected to begin on or about 04/12/18 and to finish on or before 04/20/18. Please notify anyone in your area that this process may impact.



North County Campus Emergency Alarm Testing

Location: North County Campus

Date(s) in Effect: Tuesday 4/10/18 through Friday, 4/13/18

Description: The North County Campus Center project’s construction personnel will be periodically testing the emergency alarm system beginning Tuesday, 4/10/18, and continue through Friday, 4/13/18. Testing of the audible and visual alarms at the Campus Center may be heard and seen throughout the campus. Please notify anyone that this work may impact.



SLO Instructional Building Stair Tread Repair

Location: San Luis Obispo Campus

Date(s) in Effect: Monday, 4/2/18 through Friday, 4/6/18

Description: The San Luis Obispo Instructional Building project’s construction personnel will be repairing the limestone treads at both the interior and exterior stairs beginning April 2nd and going through the end of the week. The contractor will be repairing the exterior stairs beginning the first part of this week and will then move on to the interior stairs once completed. While repairs are being made to the exterior stairs, there will be access to the second floor through the interior stairs or elevator. While repairs are being made to the interior stairs, there will be access to the second floor through the exterior stairs and elevator. Please notify anyone that this work may impact. If you have any questions, please contact the Facility Services at 805-546-3283.



SLO Campus Sewer Line Replacement

Location: San Luis Obispo Campus

Date(s) in Effect: Thursday, 3/29/18 through Sunday, 4/8/18

Description: The San Luis Obispo Campus Sewer Line Replacement project is scheduled to begin on Thursday, 03/29/18 with an anticipated completion date of Sunday, 04/08/18. Construction personnel will be removing and replacing a sewer line where indicated on the map. During this time, there may be an increase in noise, dust, construction traffic. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



SLO Campus Aquatics & Data Center Staging Area Winterization Project

Location: San Luis Obispo Campus

Date(s) in Effect: Monday, 4/2/18 through Sunday, 4/8/18

Description: The San Luis Obispo Campus Aquatics & Data Center Staging Area Winterization project is scheduled to commence on 04/02/18 with an anticipated completion date of 04/08/18. This work will occur between the hours of 7am and 5pm Monday through Sunday. During this time you should expect increased truck traffic, dust, and noise from the construction equipment in the area indicated on the map. Please notify all parties that this work may impact. If you have any questions, please contact Facilities Services 805-546-3283.



North County Campus Fire Alarm Testing

Location: North County Campus

Date(s) in Effect: Monday 4/2/18 through Friday, 4/6/18

Description: The North County Campus Center project’s construction personnel will be periodically testing the fire alarm system beginning Monday, 4/2/18, and continue throughout the week. Testing of the audible alarms at the Campus Center may be heard through-out the campus. Please notify anyone that this work may impact.



Aquatics Center Women’s Locker Room Closure

Location: San Luis Obispo Campus

Date(s) in Effect: Monday 4/2/18 through Sunday 4/8/18

Description: The Aquatic Center & 1000 Complex ADA project’s construction personnel will be adding a temporary partition wall in building 1100 from Monday, April 2, 2018 through Sunday, April 8, 2018. The women’s locker room in building 1100 will be CLOSED during this time. Please use the temporary women’s locker room identified in building 1000. THE LOCKERS IN THE WOMEN’S LOCKER ROOM WILL BE INACCESSIBLE FROM 4/2/18-4/8/18. PLEASE REMOVE ALL PADLOCKS & PERSONAL BELONGINGS FROM BLDG 1100 ON OR BEFORE FRIDAY 03/30/18. Please contact Facilities Services (805) 546-3283 if you have any questions.



SLO Instructional Building Stump Grinding

Location: San Luis Obispo Campus

Date(s) in Effect: Tuesday 1/30/18 through Friday 2/4/18

Description: The San Luis Obispo Instructional Building project’s construction personnel will be clearing the area highlighted on the map below beginning Tuesday, January 30, 2018 and grinding tree stumps on Friday, February 2, 2018. You may notice an increase in dust and noise during this time. Please notify anyone that this work may impact.