Construction Alerts Archive
HVAC Work On Building 4400 – REVISED
Location: San Luis Obispo
Date(s) in Effect: 1/27/21 – 2/16/21, 7am-4pm
Description: Contractors will begin work on Building 4400. This work will consist of demoing existing HVAC equipment and installing new HVAC. Please be advised there will be no heating or cooling in Building 4400 for duration of impact. Please be advised that moderate noise levels may be heard at times.
HVAC Work On Building 4300
Location: San Luis Obispo
Date(s) in Effect: 1/19/21 – 2/9/21, 7am-4pm
Description: Contractors will begin work on Building 4300. This work will consist of demoing existing HVAC equipment and installing new HVAC. Please be advised there will be no heating or cooling in Building 4300 for duration of impact. Please be advised that moderate noise levels may be heard at times.
Rework Taking Place On Parking Lot 11 Entrance
Location: North County Campus
Date(s) in Effect: 1/8/21 – 1/20/21, 7am-5pm
Description: Rework will be taking place on the west drive aisle entrance to Parking Lot 11. This work will extend outside of the current construction fencing. Please be advised area of work will be barricaded off and entrance will be closed off for duration of impact. Parking Lot 11 will remain open. Moderate noise is to be expected.
Wireless & TR Installation In Buildings 4100, 4200, 4300, 4400, 4500, 4600, 4700, 5100, 5300, 6200, 7100
Location: San Luis Obispo
Date(s) in Effect: 1/5/21 – 2/8/21, 6am-4:30pm
Description: The general contractor will continue performing wireless and TR installation in Building 4100, 4200, 4300, 4400, 4500, 4600, 4700, 5100, 5300, 6200, 7100. Contractor will be installing new data cabling, wireless access points and telecommunications equipment enclosures. Please be advised all wired and wireless network access, including internet access will be down for duration of impact. Area of work is noted on the associated map. Construction noise is to be expected.
Wireless & TR Installation in Buildings 6100 & 6300
Location: San Luis Obispo
Date(s) in Effect: 12/23/20 – 1/8/21, 6am-4:30pm
Description: The contractor will be performing the wireless and TR installation in Building 6100, and 6300. Area of work is noted on the associated map. Please be advised internet access will be down for duration of impact. Noise is to be expected.
Wireless & TR Installation in Building 5400
Location: San Luis Obispo
Date(s) in Effect: 12/23/20 – 1/5/21, 6am-4:30pm
Description: The contractor will be performing the wireless and TR installation in Building 5400. Area of work is noted on the associated map. Please be advised internet access will be down for duration of impact. Noise is to be expected.
Wireless and TR Installation in Buildings 6100 & 6300
Location: San Luis Obispo
Date(s) in Effect: 12/23/20 – 12/26/20, 6am-4:30pm
Description: The contractor will be performing the wireless and TR installation in Building 6100, and 6300. Area of work is noted on the associated map. Please be advised internet access will be down for duration of impact. Noise is to be expected.
Rework Taking Place At Parking Lot 11 entrance
Location: North County Campus
Date(s) in Effect: 12/18/20 – 12/24/20, 7am-5pm
Description: Rework will be taking place on the west drive aisle entrance to Parking Lot 11. This work will extend outside of the current construction fencing. Please be advised area of work will be barricaded off and entrance will be closed off for duration of impact. Parking Lot 11 will remain open. Moderate noise is to be expected.
New Telephones In Entire North County Campus & San Luis Obispo Campus
Location: Entire North County Campus & San Luis Obispo Campus
Date(s) in Effect: 12/7/20 – 12/18/20, 10am-4pm
Description: The District’s VoIP Telephone Consultants will be onsite placing new telephones in classrooms, offices, and other department areas. *As a reminder, please do not attempt to operate the new phones until directed*
Performing New Duct Work & Re-roofing on Building 7100-Annex
Location: San Luis Obispo
Date(s) in Effect: 12/8/20 – 12/23/20, 7am-3:30pm
Description: Contractors will be performing new duct work, and re-roofing on Building 7100-Annex roof above room 7107. Please be advised power to the HVAC unit above Room 7107 will be shut down for the duration of impact. Area of work is noted on associated map. Moderate noise is to be expected.