SLO Campus Center Building 7300 Data Racks

Location: (SLO) 7300 (CPAC) Telecom Room

Date(s) in Effect: February 5, 2024 – February 23, 2024

Description: Contractor will be installing new network and audio-visual racks in building 7300. This work will result in a complete building outage of the data network, WiFi, and VoIP systems for the duration.



SLO Campus Wayfinding & Signage (DSA)

Location: (SLO) Campus-Wide Wayfinding & Signage (DSA)

Date(s) in Effect: January 10, 2024 – February 23, 2024

Description: The contractor will begin installing campus I.D. building signs, street signs, and parking permit signs. All affected buildings/areas are highlighted in the associated map. The contractor will use cones to redirect pedestrian traffic around work zones when needed. Noise is to be expected.



North County Campus N2400 Classroom Interior Paint

Location: (NCC) N2400 Interior Classrooms

Date(s) in Effect: December 16, 2023 – January 8, 2023

Description: Contractor will perform interior painting in N2400 classrooms. Please be advised classrooms in N2400 will be inaccessible to students and staff, except for 2411. Interior painting in classroom 2411 will begin on December 18th, after the last class is held. Area of work is noted on the associated map. Noise is to be expected.



SLO Campus – 5000 & 6000 Complexes Switchgear

Location: (SLO) 5200/6100 Switchgear Replacement

Date(s) in Effect: December 18, 2023 – January 12, 2024

Description: Contractor will be performing switchgear installations within the 5000 and 6000 complexes. Both complexes will be without power for the duration of this installation. However, temporary power will be established for the Buildings 5200 and 5600-5900 only. Additionally, there will be a campus-wide power shutdown from December 26th to December 29th. The main areas of impact are noted on the associated map. Noise is to be expected.



SLO Campus – Parking Lot 6, near Building 1000 – Concrete Pour

Location: (SLO) Parking Lot 6

Date(s) in Effect: December 1, 2023; 7am - 4pm

Description: Contractor will perform concrete pour in Parking Lot 6, near Building 1000. Please be advised the area of work will be closed off with caution tape. Vehicle and pedestrian traffic may be interrupted during this time. However, the walkway will remain open. Noise is to be expected.



Building 7100 HVAC Replacement

Location: (SLO) Building 7100

Date(s) in Effect: November 21, 2023; 10 am – 4 pm

Description: Contractor will remove and replace an HVAC unit, located on the south side of Building 7100. A crane will be utilized from the fire lane adjacent to Parking Lot 2. The ceramics yard will be closed for staff and student safety. Area of work is noted on the associated map. Noise is to be expected.



NCC Campus Center Signage

Location: (NCC) Campus Center

Date(s) in Effect: November 9, 2023 – November 17, 2023; 7 am - 4 pm

Description: Contractor will be onsite to install the remaining interior and exterior building signage for the NC Campus Center. The contractor will be utilizing lifts, ladders, and possibly scaffolding to install overhead signage. All work zones will be coned off, but pedestrians should use caution when passing these areas. Some noise is to be expected.



SLO 4000s Complex Fire Alarm Test P2

Location: (SLO) 4000s Complex

Date(s) in Effect: October 24, 2023; 6:45 am – 7:45 am

Description: District personnel will be conducting fire alarm testing in the 4000s complex. Audible bells and visual strobes will be actuated. The areas of impact are noted on the associated map. Noise is to be expected.



Building 5300 Tile Replacement

Location: (SLO) Building 5300

Date(s) in Effect: October 23, 2023 – November 3, 2023, 6am - 4pm

Description: The contractor will be onsite to remove and replace existing underlayment and reinstall roof tiles at Building 5300. Please be advised ladders and lifting equipment will be utilized. The pathway between Building 5300 and Building 1300 will be closed and utilized as a laydown area. Noise is to be expected.



NCC Campus Center Signage & Wayfinding

Location: (NCC) Campus Center Building N1000/N1100

Date(s) in Effect: October 23, 2023 – October 27, 2023, 7am - 4pm

Description: Contractor will be onsite installing interior and exterior building signage for the North County Campus Center. Please be advised ladders and lifting equipment will be utilized. Pedestrians should use caution in areas of installation. Area of work is noted on the associated map. Some noise is to be expected.