1000 Complex Renovations Project – 05-31-19 Weekly Construction Update
Work this week: Temporary fencing and scaffolding were installed…
Work this week: Temporary fencing and scaffolding were installed…
Monthly status update on all existing Measure L projects.
Monthly status update on all existing Measure L projects.
Work this week: Construction crews are continuing to work in the pool equipment room…
Work this week: The electrical contractor has been installing new conduit and pull boxes from the new IDF rack location to the new exterior WAP locations in building 1200…
Work this week: The electrical contractor completed painting all conduits on soffits and high walls in building 1400…
Work this week: Construction crews are continuing to set tile at the competition pool…
Work this week: The electrical contractor finished installing Wireless Access Point (WAP’s) soffits in building 1400…
Monthly status update on all existing Measure L projects.
Work this week: The electrical contractor installed overhead conduit and pull boxes on soffits and high walls in building 1400…