Early Childhood Education – 07-10-20 Weekly Construction Update

Work this week: General contractor completed the mechanical well membrane roofing, as well as the scratch coat for ECE’s exterior plaster. The 2nd layer of brown coat system is underway. Construction team continued trenching work for the conduits that will carry the site lighting wiring, and remainder of the metal roofing install. Electrical and Communication systems are currently being hooked up.