North County Campus Interim Housing Landings

Location: North County Campus

Date(s) in Effect: Monday, 9/21/15

Description: Construction personnel working on the North County Campus Interim Housing Project will be working on the landings of the modular buildings on Monday, 9/21/15 and is scheduled to be complete by the end of the day. The landings are highlighted below and will be identified by delineators while they are working in these areas. Access to the buildings will not be impacted.



San Luis Obispo Campus Parking Lot 3 Repairs

Location: San Luis Obispo Campus

Date(s) in Effect: Friday, 9/18/15 through Saturday, 10/31/15

Description: As of Friday, 9/18/15, two ADA parking spaces in Parking Lot 3 are closed for repairs and have been coned-off with orange delineators. The date of the repair is tentatively schedule to be complete 10/31/15. Once confirmed, an updated construction alert will be forthcoming.



North County Campus Interim Housing Landings

Location: North County Campus

Date(s) in Effect: Monday, 9/14/15

Description: Construction personnel working on the North County College Campus Interim Housing Project will be working on the landings of the portable buildings on Monday, 9/14/15. The landings are highlighted on the map and will be identified by delineators while they are working in these areas. Access to the buildings will not be impacted.



North County Campus Interim Housing Fence Installation

Location: North County Campus

Date(s) in Effect: Friday, 9/11/15 though Thursday, 9/17/15

Description: North County Campus Interim Housing will have a fence installed between the new portable buildings on the south east side, near the cafeteria trailer, starting on Friday,  9/11/15. Work will continue through Thursday, 9/17/15.



San Luis Obispo Campus HVAC/ Roofing Replacement Materials Hoisting

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 8/26/15 through Friday, 8/28/15

Description: San Luis Obispo Campus Roofing HVAC Replacement Project will be hoisting materials onto the highlighted roofs on the map from Wednesday, 8/26/15 through Friday, 8/28/15. Expect spotters at ground and roof level while the forklift is loading and unloading materials onto the roof. The forklift will be in operation from 6:00am to 8:00am. This will occur at Buildings 1100, 4500 & 4600.



San Luis Obispo Campus Interim Housing Fire Alarm Testing

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 8/5/15 through Thursday, 8/6/15

Description: San Luis Obispo Campus Interim Housing Project will be subject to a Fire Alarm Test from Wednesday, 8/5/15 through Thursday, 8/6/15. Expect intermittent noise (audible) from fire alarm devices during this period. The alarms will only be triggered in the highlighted areas below. The remainder of the campus alarms will be unaffected.



San Luis Obispo Campus Parking Lot 3 Rescheduled Demolition

Location: San Luis Obispo

Date(s) in Effect: Friday, 7/24/15 through Monday, 7/27/15

Description: Update: The San Luis Obispo Campus Parking Lot 3, adjacent to the public safety building, is tentatively rescheduled to undergo demolition and paving on Friday, 7/24/15. The highlighted area on the map will be closed during the construction activity. The closed section will see new paving and re-striping. Additional signage and finishes will be completed on Monday, 7/27/15.



San Luis Obispo Campus Roof/HVAC Replacement

Location: San Luis Obispo Campus

Date(s) in Effect: Thursday, 7/23/15 until completion

Description: San Luis Obispo Campus Roof/HVAC Replacement Project, is scheduled to start this week on Thursday, 7/23/15. Buildings 1100, 4500 & 4600 will be closed for the duration of construction. The buildings will see new HVAC equipment and new roofing material. Temporary fences will be installed to close off the buildings.



San Luis Obispo Campus Interim Housing Fire Alarm Testing

Location: San Luis Obispo Campus

Date(s) in Effect: Wednesday, 7/22/15 to Monday 7/27/15

Description: The San Luis Obispo Campus Interim Housing Project will be subject to a Fire Alarm Test from Wednesday, 7/22/15 to Monday 7/27/15. Expect intermittent noise (audible) from fire alarm devices during this period. The alarms will only be triggered in the highlighted areas below. The remainder of the campus alarms will be unaffected.



North County College Campus Interim Housing Fire Alarm Testing

Location: North County Campus

Date(s) in Effect: Thursday, 7/16/15 through Monday, 7/20/15

Description: North County College Campus Interim Housing Project will be subject to Fire Alarm Testing beginning Thursday, 7/16/15 through Monday, 7/20/15. Expect intermittent noise (audible) from fire alarm devices during this period. The alarms will only be triggered in the highlighted area on the map. The remainder of the campus alarms will not be affected by the testing.