Asphalt Resurfacing Phase II – 10-23-20 Weekly Construction Update

Work this week: The general contractor continued demo on existing driveways at parking lot 2 along with a section of damaged asphalt. Sidewalk ramps have been demoed and concrete forms and rebar set in place. Excavation and grading remain ongoing at parking lot 1, along with concrete form work.

Download PDF →