4k, 5k, 6k Restroom & Drinking Fountain ADA Upgrades – 01-20-23 Weekly Construction Update

Work this week: Contractor installed toilet partitions in 4300 restrooms. Framing work is in progress in 6200. Restrooms at 5100 are substantially complete, pending fire alarm and door hardware. Painting has been completed in 4200, adjacent to drinking fountain/eyewash stations.